OUR HISTORY
PROJECT TIMELINE
2009 - 2017
30 November -0001
555-555-0199@example.com

08 December 2009
Bid+submission.

10 August 2010
Signing+of+the+Power+Purchase+Agreement.

18 August 2012
Early+power+Commencement+Date.

04 April 2013
Project+Commercial+Operation+Date+achieved.

23 June 2014
First+Listing+on+Muscat+Stock+Market

11 July 2009
Request+for+proposal+issued+by+OPWP.

30 May 2010
Declaration+as+%27preferred+bidder%27

24 September 2010
Final+Notice+to+Proceed+to+the+Engineering%2c+Procurement%2c+Construction+Contractor+%28EPCC%29.

30 September 2012
End+of+early+power+period.

24 March 2014
Inauguration+under+the+patronage+of+H.E.+Mohammed+bin+Salim+bin+Said+Al+Tobi%2c+Minister+of+Environment+and+Climate+Affairs%2c+Sultanate+of+Oman.